Five things that change your drawings

Load Path is our short monthly note for architects on what is changing in house structures, and what it means for your drawings. Each item links to its source.

Download the issue PDF, 4 pages, 1 MB

Illustrative image: a new steel beam in red primer spanning a wide opening in a brick wall, each end bearing on a concrete padstone on a brick pier.
AI-generated illustration: a new steel beam over a knock-through, each end on a padstone.

Illustrative image

Changelog

Rule changes for house work, release-note style

  • Added

    BS EN 1990-1:2023+A1:2026 and its UK National Annex: the basis of design for new structures.

    BSI, 13 October 2026

  • Added

    BS EN 1990-2:2026: assessing existing structures. Replaces PD CEN/TS 17440:2020.

    BSI, 13 October 2026

  • Changed

    Steel imports, from 1 July 2026: tariff-free quotas 51% lower; a 50% tariff above the quota.

    GOV.UK, updated 3 November 2026

  • Coming

    Future Homes and Buildings Standards, 24 March 2027. The current rules apply only where notice goes in before 24 March 2027 and work starts before 24 March 2028.

    GOV.UK, 24 March 2026

    1
  • Coming

    NHBC Standards 2027: homes whose foundations begin on or after 1 January 2027. New chapter 3.4.

    NHBC

  • Deprecated

    First-generation Eurocodes: due to be withdrawn on 30 March 2028. Both generations run side by side until then.

    BSI, 13 October 2026

Delta 1 marks the change most likely to alter a drawing this month.

Regulations

The Future Homes Standard now has fixed dates

Illustrative image: a cavity wall under construction, with an aircrete inner leaf, insulation boards, wall ties across the cavity and a brick outer leaf.
AI-generated illustration: a cavity wall going up. If the cavity widens, the ties and lintels change with it.

Illustrative image

The Future Homes and Buildings Standards come into force in England on 24 March 2027. Work stays under the current rules only if the building notice, initial notice or full plans application goes in before 24 March 2027 and the work starts before 24 March 2028.

On your drawings

For a new house, settle the wall build-up early. If the insulation gets thicker and the cavity wider, the wall ties, lintels and the way steel beams bear on the inner leaf change with it, so we need the build-up before we size anything.

Source: Building Circular 01/2026, GOV.UK, 24 March 2026

Standards

The second-generation Eurocodes are arriving

In October BSI set out three new standards. BS EN 1990-1:2023+A1:2026 and its UK National Annex set the basis of design for new structures. BS EN 1990-2:2026 is a new standard for assessing existing structures, and replaces PD CEN/TS 17440:2020. The first-generation Eurocodes are due to be withdrawn on 30 March 2028, and until then the two generations run side by side.

On your drawings

Nothing changes yet, though calculations may start to cite the new codes before the old ones are withdrawn. For alterations, BS EN 1990-2 gives a recognised way to assess an existing house as it stands, rather than as if it were new.

Source: BSI, 13 October 2026

Costs

Tariff-free steel imports cut by half

Illustrative image: four new steel I-section beams in red primer lying on timber bearers in a steel stockholder's yard.
AI-generated illustration: universal beams at a stockholder.

Illustrative image

Since 1 July 2026 the UK has limited tariff-free steel imports, with quotas 51% lower than under the old safeguard. Steel imported above the quota pays a 50% tariff. Beams, angles and hollow sections are all in scope.

On your drawings

Do not carry a steel price from an old quote into a client’s budget. Get a current price and lead time, and tell us early if the budget is tight: common section sizes are usually easier to get.

Source: UK’s steel trade measure from 1 July 2026, GOV.UK, updated 3 November 2026

Lessons

I-joists in a house fire

Illustrative image: the underside of a new timber floor of engineered I-joists sitting in steel hangers, before the ceiling is fitted.
AI-generated illustration: I-joists before the ceiling goes up. Not the house in the report.

Illustrative image

CROSS-UK Report 1550 describes a fire in a two-storey semi-detached house with I-joists that had OSB webs. Part of the floor near the stair collapsed once the webs burned away, and no fire-stopping was found above an internal load-bearing wall. The panel’s view is that such systems are “generally compliant” but “may be vulnerable to early loss of structural integrity”. For designers, the report asks that fire-stopping in concealed voids be “capable of being verified during construction”.

On your drawings

Where I-joists are specified, detail the ceiling linings and the fire-stopping in the floor voids, especially round the stair, and say when they are to be inspected before they are boarded over.

Source: CROSS-UK Report 1550, 10 June 2026, updated 20 July 2026

In court

An extension built over the gas pipe

A Bradford building company built an extension over the gas service pipe and left the boiler flue ending inside the new room. The gas network found it immediately dangerous and cut the supply. On 7 August 2026 the company was fined £10,000 with £4,263 costs, and its director £1,000. The Health and Safety Executive’s reminder: everyone in control of domestic building work must have “a suitable and sufficient construction phase plan”.

On your drawings

Show flues, gas meters and service runs on the survey and the proposed plans, and say who moves them before the footprint is set out.

Source: Health and Safety Executive press release, 17 August 2026

Illustrative image: a street of English houses drawn as a laser-scan point cloud in teal, with a lime scan line passing across it.

AI watch

How AI is changing house work

In every issue · November 2026

Illustrative image: a printed ground floor plan of a house with a rear extension; the extension's walls are traced in teal light, with lime dots at the corners.
AI-generated illustration: software tracing the walls of an extension on a householder plan.

Illustrative image

Councils start using AI on householder applications

PlanAssist, a government AI tool, puts an application, the local policies and the site constraints in one place and gives the planning officer a first assessment; officers still decide. In testing it cut time on key tasks by 58%, and the government says that halves processing times for routine householder applications, from eight weeks to four. It is now being tried in 15 councils, none of them in Surrey, and the aim is every council in England by the end of 2027.

For your projects

If permission comes back in four weeks, the structural design can become the hold-up. Bring the engineer in at sketch stage.

Source: Faster planning decisions as new rules and AI tackle delays, GOV.UK, 30 October 2026

Also: CROSS-UK Report 1554 (16 July 2026): unchecked AI output was used to justify heavy plant on an existing roof. A beam size from an online tool is a guess until an engineer has checked it. Report 1554

Worth attending: the webinar AI in structural engineering, 1 December, 12:00 to 13:15, online. Details

Quick question

Has a client brought you something made with AI this year: a layout, a render or a beam size?

Each answer opens an email to us with the answer filled in. Results in December’s issue.

In brief

  • NHBC Standards 2027 apply to every home under NHBC cover whose foundations are begun on or after 1 January 2027. A new chapter 3.4 covers materials in aggressive coastal environments. NHBC Standards
  • Worth sending to clients. A free guide for homeowners, Introduction to structural engineering for domestic clients (25 June 2026), explains what an engineer does on a house project and ends with a homeowner’s checklist. One point saves arguments later: the dimensions in an engineer’s calculations are not for ordering steel or lintels, and the contractor should measure before anything is fabricated. Read the guide
  • Worth reading. The Structural Engineer is running a series, Large openings in domestic structures: Part 1, steel moment frames (3 August 2026), and Part 2, foundations (1 October 2026). Free to members and subscribers. Part 1 · Part 2

Back page

Spot the fault

Three things in this picture would worry us. How many can you find?

Illustrative image: a rear knock-through in progress, with a red-primed steel beam over a wide opening and two steel props under it.
AI-generated illustration, made for this puzzle. Not a real site.

Illustrative image

Show the answers
  1. The left end of the beam has no padstone. It sits on loose broken bricks and slate packing; a beam end needs a proper bearing, usually a padstone sized by the engineer and bedded in mortar.
  2. The left prop leans. Adjustable props are made to stand vertical; one at an angle is not working as designed and can kick out.
  3. That prop also stands on a broken paving slab. A prop needs a firm, level base, like the timber board under the right-hand prop.

Found something we did not list? Email us what you saw. We read every answer.

Have a house project at sketch stage?

Stage 1 or Stage 2 sketches get a free sense-check. We reply within one working day.

Or call 01483 363308: Monday to Friday 9am to 5pm, Saturday 9am to noon.