Notes
Converting a loft: what holds the roof up, and what replaces it
A loft room starts with taking away the things that hold the roof up. Here is what goes in first, and why the order matters.
Illustrative image
A loft conversion is sold as a room. Structurally it is three changes to a roof that was built for something else. The struts that hold the roof slopes up have to come out. A floor that can carry people has to go in. And, usually, a hole is cut in the roof for a dormer.
None of that is unusual, and all of it has an order. Below, the same model house as our wall article is converted one step at a time.
Step by step
How does a loft conversion change the roof?
It swaps the struts that hold the roof up for new beams, adds a new floor that can carry people, and usually cuts a dormer into one slope, in that order.
The model is a photograph of an ordinary two-storey house cut through in section. Everything drawn over it is the engineering.
What is up there now
Open the hatch of an older house with a cut roof and this is roughly what you find. The rafters are the two slopes, from the ridge down to the outer walls. Part way down each slope, a strut carries it down onto an internal wall. Across the bottom run the ceiling joists. They hold up the ceiling of the rooms below and tie the feet of the rafters together, and they were sized for plasterboard, not people.
Two kinds of roof
This model has a cut roof, built piece by piece on site. Newer houses usually have trussed rafters: triangles made in a factory, with diagonals inside them. Trussed rafters became common later in the 1945 to 1979 period and are typical from 1980; older houses usually have cut roofs. Typical for the period; we confirm it from photos.
In a trussed roof the diagonals are what hold the roof up, and none of them can be cut out. That roof needs new structure, designed as a whole, before anything is removed. The rest of this sequence is a cut roof, like the model.
The struts are in the way, and they are working
The struts stand exactly where a room wants to be. They are also doing a job: they carry the roof slopes down onto the walls below, and from there to the foundations and the ground. So they cannot go until something else does that job.
Steel goes in first
One answer is a steel beam along the ridge and a steel purlin under each slope, each drawn end on as a steel I because it runs away from you. They bear on padstones in the party wall, our half, and on the gable, out of this view. It is one way of several.
Held at the top, the rafters no longer push the walls out at the eaves. Until now the ceiling joists, and any collars, stopped that as ties.
Now one strut can go
Only now does the front strut come out, shown dashed. The rear one waits for the dormer. The order is the whole point: the new support goes in before the old one comes out, so the roof is never left with nothing holding it.
A floor for people
The new floor is a new set of joists at close centres, laid beside the old ceiling joists and clear of them, so the ceiling below carries nothing new. On this section they span front to back, between walls that run into the page: both outer walls and both internal walls. Where a span is too long for timber, a steel beam picks the joists up part way.
The model changes
The photograph is now the converted model: the struts gone, the floor in, and a full-width dormer on the right-hand slope. Everything drawn over it is still the engineering.
The dormer has its own structure
It runs from the party wall to the gable. Its frame is drawn here on its own. Rafters are cut to make the hole. Each side of it, a doubled trimming rafter runs down the slope. A steel purlin across the top carries the cut rafters above it and one end of the dormer’s flat roof joists. Those run out to the dormer face, which stands on the rear wall at the eaves. The cheeks, the side walls, are framed on the trimming rafters or the new floor.
Where the new load goes
The roof now comes down the rafters to the steels and the outer walls. The new floor hands its load to all four walls. Each wall takes it down to its foundation, and the foundation spreads it into the ground.
The steels carry their share into the page, to the party wall and the gable. None of it comes down through the room.
The stair, and next door
The new stair comes up through the new floor, so the floor needs an opening, trimmed like the dormer’s hole.
On a semi or terrace, each steel bears in a party wall, in our half, never through it. That is work to a party structure, notifiable under the Party Wall etc. Act 1996 at least two months before the work starts.
Source: Party Wall etc. Act 1996, section 3.
Illustrative image
What if you are also taking a wall out downstairs?
The new floor joists land on the internal wall on the right, which runs parallel to the front. That is the wall our wall article takes out on the ground floor. Do both, and the loft adds load to the wall the new beam has to carry, while the loft design depends on what that wall stands on. Designed together they fit; designed apart, one gets redone. It is the best reason to call early, about the whole house.
Diagram drawn for this site. Not a design.
Key to the drawings
- Existing masonry A flat tone: everything already there, cut or seen.
- Concrete Aggregate triangles and fine dots, scattered at random: foundations, slabs, padstones, lean-mix cavity fill, encasement.
- Undisturbed ground Basket weave, as a band that follows the ground line and fades out.
- Hardcore Large open zigzag, the depth of its own layer.
- Insulation board The looped line, touching both faces, inside the board outline.
- Insulation quilt The same looped line with no outline: mineral wool, loft quilt.
- Timber, cut A box with a cross. Seen along its length, an outline only.
- Steel, cut Solid, at the section's true proportion.
- Pressed steel Lintels, hangers, straps: a line at the wide weight.
- DPC Heavy dashed line, as Approved Document C draws it.
- Membrane, tray Heavy solid line: DPM, cavity tray, roof membrane.
- Load path Where the load goes, from the roof to the ground; dashed where it runs beyond the cut.
- Load marks Arrows at the symbol weight: loads down onto a member, bearing up under a foundation.
- Hidden, beyond or removed Out of the cut, beyond it, or taken out.
- By others, beyond Faint: frames, coverings. Not our structure.
- Inset zone Chain line round what is drawn again, larger, in an inset.
- Cloud Confirm on site. Never a revision mark.
- Break line The drawing stops; the building does not.
Do you need a structural engineer for a loft conversion?
Usually, yes. Building Control has to see that the new structure meets Part A, which normally takes an engineer’s calculations. If the ridge beam is steel, its span sets its weight and price.
Source: The Building Regulations 2010 (England and Wales), regulation 3.
What do we need from you for a loft?
- Existing plans and a section, if you have them.
- Photographs inside the roof space: rafters, struts, ceiling joists and where they land.
- The roof type if you know it: cut, or trussed rafters.
One more thing
Every design we do meets the Building Regulations. Lean means taking the waste out, not the safety.
The room you are left with
None of the structure is on show. It is behind the ceiling and in the floor.Illustrative image