Adding a basement under a house that is already standing
The house above is carried all the way down, next door has a say, and many London councils name the engineer who must sign. Here is what the structure has to do, and the order it goes in.
What the structure has to do
A basement is a box dug under walls that are already carrying a house. Each of those walls stands on a footing a little way below the ground. To make a room underneath, every wall has to be carried down past its old footing to a new one below the new floor. That is underpinning, and it applies to the internal walls as well as the outside ones.
Once the box is dug, its walls are retaining walls. The ground pushes on them from outside, and where there is water in the ground, the water pushes too. At the bottom, the water pushes up under the slab. So the new walls are designed to span between two floors: the base slab at the bottom, and the new ground floor at the top, which props them at their heads.
None of that is in place on the day the dig starts. That is why the order matters as much as the finished box.
The order of the dig
Illustrative. No size, depth or load is shown: the engineer sets those for each house.
- Underpin the walls in bays, while the ground in the middle stays where it is.
- Prop across between the new walls at the top, just below where the new ground floor will be, before the middle is dug.
- Dig the middle in stages, adding lower props as the design requires.
- Cast the base slab, which props the walls at the bottom. The lower props come out only once it has gained the strength the design sets.
- Build the new ground floor, tied to the walls, then take the top props out.
Key to the drawings
- Existing masonry A flat tone: everything already there, cut or seen.
- Concrete Aggregate triangles and fine dots, scattered at random: foundations, slabs, padstones, lean-mix cavity fill, encasement.
- Undisturbed ground Basket weave, as a band that follows the ground line and fades out.
- Hidden, beyond or removed Out of the cut, beyond it, or taken out.
- Temporary works, our design Teal line work: needles, props, sole plates, runners, walings, linings. Boxed tags, TW1 and up. Packing is drawn in the dry pack stipple.
- Temporary works, struck Teal, dashed: taken out at this stage.
- Break line The drawing stops; the building does not.
Illustrative. The number of bays, and how many stand open at once, is set by the design.
The order skips along the wall, so the wall is never hanging over two open bays side by side. In the drawing it runs U1, U4, U2, U5, U3: a bay’s number is its name, not its place in the order.
On the jobs we take, we design the temporary support and the order of the dig. The builder puts them in, maintains them and takes them out to our drawings, in the order they show. We check every temporary works design before it is issued.
Next door
A basement nearly always brings in the Party Wall etc. Act 1996. Underpinning a party wall is one of the Act’s rights, and it needs notice at least two months before the work starts. Digging within 3 m of next door and below its foundations needs notice at least one month before. If next door does not consent within 14 days of a notice, the Act treats that as a dispute, and a party wall award settles it.
The Act puts the duty to serve notice on you, the building owner. Our page on party wall surveys sets out the notices, the surveyors and the award.
Party Wall etc. Act 1996, sections 2(2)(a), 3(2)(a), 5, 6(1), 6(5), 6(7) and 10(10), legislation.gov.uk.
Who must sign what, borough by borough
Most London councils ask for a basement impact assessment, a structural method statement or a construction method statement with a basement application. Fourteen of the 33 go further and name the title of whoever must prepare or sign one.
| Council | What it asks for | Who must sign, in the council’s words | Where it says so |
|---|---|---|---|
| Camden | Basement impact assessment: the land stability part | A Civil Engineer with the ‘CEng’ (Chartered Engineer) qualification from the Engineering Council and a Member of the Institution of Civil Engineers (‘MICE’) |
Camden Planning Guidance: Basements (January 2021), paragraph 4.7 and its table |
| Enfield | Structural method statement, on applications other than householder ones | prepared and self-certified by a suitably qualified chartered engineer, who is a member of the relevant professional body |
Local Validation Requirements, all applications except householder (March 2024), item 14 |
| Greenwich | Structural method statement, with a basement impact assessment | should be signed off and endorsed by a Chartered Civil Engineer or Chartered Structural Engineer with relevant experience |
Local Validation Requirements List (June 2025), basement impact assessment |
| Havering | Structural survey, wherever a basement is proposed, householder applications included | prepared and self-certified by a suitably qualified chartered engineer, who is a member of the relevant professional body |
Planning Application Checklist 001, householder applications, structural survey |
| Islington | Structural method statement | must be signed and endorsed by a Chartered Civil Engineer or Chartered Structural Engineer with relevant experience, appointed by the applicant |
Local Plan (September 2023), paragraph 8.63 |
| Kensington and Chelsea | Construction Method Statement | The CMS must be signed by a Chartered Civil Engineer (MICE) or Chartered Structural Engineer (MI Struct. E.) |
Basements Supplementary Planning Document (April 2016), paragraph 5.2 |
| Kingston upon Thames | Basement impact assessment, householder applications included | A Basement Impact Assessment must be carried out and signed by a Chartered Civil Engineer or Chartered Structural Engineer |
Householder Validation Local List (February 2024) |
| Lambeth | Basement impact assessment | The qualification required to prepare a BIA is Chartered Engineer, Member of MICE, C.WEM, CGeol |
Lambeth Local Plan (September 2021), paragraph 10.137 |
| Merton | Structural methodology statement, with every basement application | must be prepared and signed off by a Chartered Civil Engineer (MICE) or Structural Engineer (MI Struct.E) |
Basement and Subterranean Planning Guidance (March 2017), paragraph 10.22 |
| Redbridge | Basement impact assessment | must be carried out and signed by a Chartered Civil Engineer or Charted Structural Engineer(its spelling) |
Validation List (August 2026), basement impact assessment |
| Richmond upon Thames | Screening assessment and basement impact assessment, in its throughflow and groundwater zones; structural impact assessment, for listed buildings | undertaken by a chartered professional; for listed buildings, prepared and signed off by a Chartered Civil Engineer (MICE) or Structural Engineer (MI Struct.E) |
Local Plan 2024 to 2039 (October 2025), paragraph 25.58; Good Practice Guide on Basement Developments (May 2015), paragraph 5.1 |
| Waltham Forest | Basement impact assessment, householder applications included | prepared and self-certified by a suitably qualified chartered engineer or chartered geologist, who is a member of the relevant professional body |
Householder Planning Application Checklist 2025, basement impact assessment |
| Wandsworth | Construction management plan, for basements | The CMP must be signed by a Chartered Civil Engineer (MICE) or Chartered Structural Engineer (MI Struct. E.) |
Local Validation Checklist (July 2026), item 29 |
| Westminster | Structural methodology statement and its self-certification | A Chartered Civil Engineer (MICE) or Structural Engineer (MI Struct.E) |
Local List of Validation Requirements (July 2026), item L39 and its footnote 32 |
The fourteen include Kingston, Merton and Wandsworth, and Richmond in its throughflow and groundwater zones and for listed buildings. We do not sign those documents, so we do not take basement work where these rules apply. If you are planning a basement there, appoint an engineer with the title the council names. The other councils’ documents we read name no title for whoever signs.
Outside London, none of Surrey’s eleven councils, nor Horsham, Mid Sussex or Brighton and
Hove, names such a title for a basement document. Guildford’s plan asks for a structural
impact report from a certified structural engineer
(Local Plan: Development Management Policies (March 2023),
Policy H4) and does not say what it means by that.
Councils change these rules, and a new local plan can move them. The table was read on : check the council’s current guidance before you apply.
What we need to start
Plans and a section of the house, and what you know about the ground and the water. A basement is quoted for each project (fees).